Restoration Environmental Contractors provided an experienced project management
team and highly trained work force specialized in decontamination, abatement and
environmental plant cleaning services. MacViro Consultants Ltd. were the hospital's
environmental consultants and monitored this project.
We
successfully removed the Fly Ash from the Hospital Incinerator Waste Disposal Facility.
The Hospital Incinerator and Waste Disposal Facility did require industrial cleaning and
environmental decontamination. The Garbage Collection and Compaction Area required removal
of all remaining garbage and debris plus washing and neutralization of the area to
eliminate the remaining strong odor.
Restoration Environmental
Contractors Project Management Team has over 300,000 hours of experience. All work was
completed following Ontario Regulations Type 3 Operation Procedures and US-EPA Asbestos
and Lead Abatement regulations. |